Interenergo launches its first wind farm in Bosnia and Herzegovina

Interenergo launches its first wind farm in Bosnia and Herzegovina

Photo: Interenergo

Published

May 27, 2025

Comments

comments icon

0

Share

Published:

May 27, 2025

Comments:

comments icon

0

Share

The Ivan Sedlo wind farm, located on the mountain of the same name in the municipality of Hadžići, is the first power-generating wind facility in Sarajevo Canton. The project was developed by Slovenian company Interenergo, owned by Austria-based energy group Kelag. It is it’s first wind power plant in Bosnia and Herzegovina.

With a total installed capacity of 25 MW, the wind farm is equipped with five Siemens Gamesa 5.0 turbines. According to the company’s update, the wind farm will generate enough green electricity to power approximately 11,000 households in Bosnia and Herzegovina and prevent over 32,000 tons of CO2 emissions annually.

The construction of the Ivan Sedlo wind farm began in late September 2022, following more than six years of preparation. Interenergo acquired the project from the previous investor, Suzlon Energy BH, a company owned by Danish firm Suzlon Wind Energy.

“We’re proud to launch our first wind project in Bosnia and Herzegovina. Despite challenging site conditions, the project was delivered without major delays or compromises in quality. This achievement reflects the strong cooperation we’ve built with the Municipality of Hadžići and the surrounding communities, whose support was vital throughout the development process”, stated David Huber, Director of Interenergo.

According to him, the wind farm is expected to generate over 65 GWh annually, marking a significant milestone in the development of clean energy for Hadžići, Bosnia and Herzegovina, and the wider Balkan region.

opening of Interenrgo first wind park in Bosnia and Herzegovina
Photo: Interenergo

“The importance of the investment for the local community is diverse — from a cleaner environment and new jobs to additional funds for the Municipality of Hadžići’s budget. I believe this is just the beginning, as we have a clear goal: the development of environmentally sustainable, long-term profitable, and socially responsible energy solutions. We also have the potential and the will to continue in that direction,” said Eldar Čomor, Mayor of Hadžići.

Nihad Uk, the prime minister of Sarajevo Canton, emphasized at the inauguration that projects like this are becoming increasingly important because, as he said, it’s not a question of years, but months before the European Union introduces so-called carbon taxes.

Interenergo has been active in the Bosnia and Herzegovina market since 2007.  Today, in addition to the wind park, the company operates eight hydropower plants with a total capacity of 43 MW and an average annual production of over 125 GWh — enough to supply more than 31,000 households and avoid 61,500 tons of CO2 emissions each year.

By 2032, Interenergo plans to develop new renewable energy projects across the region, aiming to add more than 300 MW of new capacity.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

ACER Zinglersen Integrate electricity markets flexibility new era already here BEF 2025

ACER’s Zinglersen: Integrate electricity markets to bolster flexibility as new era is already here

28 May 2025 - The number of hours with negative power prices reached an all-time high for two years in a row, which means a new era is here, ACER's Director Christian Zinglersen said at BEF 2025

NGEN BEF 2025 decentralized electricity grid Roman Bernard BEF 2025

NGEN showcases solutions at BEF 2025 for decentralized electricity grid of tomorrow

28 May 2025 - Slovenia-based NGEN is expanding throughout Europe with its software platforms and equipment and BESS for decentralized grids

belgrade energy forum bef 2025 flexibility services batteries koer ngen ems alteo cybergrid

BEF 2025: Digitalization, open markets, time are major preconditions for flexibility services mainstreaming

27 May 2025 - The panel called Market Flexibility: The Backbone of a Resilient Energy System was one of the eight sessions at Belgrade Energy Forum 2025

Fortis Energy Gavrilovic developing huge portfolio in SEE

Velimir Gavrilović, Fortis Energy: We are developing huge portfolio in SEE

27 May 2025 - Fortis Energy is working on renewable energy projects of 2 GW altogether in Southeast Europe, of which half is in Serbia