Renewables

Small Greek investors in renewables face cancellations of projects on distribution level

Small Greek investors faced with cancellations for renewable energy projects in the distribution network

Photo: This_is_Engineering on Pixabay

Published

July 9, 2024

Country

Comments

comments icon

0

Share

Published:

July 9, 2024

Country:

Comments:

comments icon

0

Share

The Hellenic Electricity Distribution Network Operator (HEDNO) stopped accepting applications for renewable energy plants in 2022 as a result of the distribution network’s inability to handle new installations.

Lately, a new obstacle has appeared for small investors aiming to connect to the distribution grid. Last month, HEDNO began to cancel applications from 2019 as five-year deadlines expired.

It is expected to affect thousands of projects currently in the waiting line and create a licensing gap as month after month more applications will be cancelled. Small investors are asking the government for an extension to be able to materialize their plans.

They argue that they already paid large sums, EUR 20,000 to EUR 40,000 per project through the procedure for their letters of intent and other regulatory requirements, and undertaken significant risk.

EUR 539 million to upgrade substations

Recently, HEDNO published its new five-year development plan for public consultation. According to the latest data, at the beginning of 2024 there were 7.5 GW of operational renewable energy plants connected to the country’s distribution grid. Most (around 6 GW) are found in the mid-voltage segment, and the rest in low voltage.

The vast majority of the capacity are photovoltaics (5.95 GW) while wind power reached 1.08 GW and small hydroelectric plants amounted to 252 MW.

Manos: National goals cannot be achieved without grid investments

HEDNO aims to spend EUR 539 million on new user connections by 2028. More specifically, the company plans to upgrade 14 substations using funds from the European Union’s Recovery and Resilience Facility (RRF) and 18 others with its own funds, as well as to support the installation of two private substations.

Furthermore, substations in congested areas are intended to be upgraded from 7.2 kA to 10 kA after the completion of relevant studies.

National goals in renewable energy production and electric mobility will not be achieved without investing in grids, HEDNO’s CEO Anastasios Manos warned in April.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

bulgaria sunotec sungrow bess battery storage

Sunotec, Sungrow sign 2.4 GWh battery storage agreement

29 July 2025 - China-based Sungrow and Bulgarian-German company Sunotec have agreed to install 2.4 GWh of battery energy storage systems in Europe

Two small hydropower turbines to be integrated with Sofia water supply lines

Two small hydropower turbines to be integrated into Sofia water supply lines

28 July 2025 - Veolia received a green light from Bulgaria's capital city to install two hydropower generators within the city's major water supply lines

slovenia geothermal energy verde energy soyak concession

Slovenia awards first concession for geothermal exploration

28 July 2025 - It is the first concession awarded for geothermal energy, marking an important step toward decarbonizing the Pomurje region

Romania EUR 300 million subsidies geothermal heating cooling

Romania preparing EUR 300 million in subsidies for geothermal heating, cooling

28 July 2025 - A proposed state aid mechanism for geothermal district heating or cooling systems in Romania would be worth EUR 300 million