CGES signs grid connection agreement for 240 MW solar power plant

cges grid connection agreement ee korita european energy asanovic banovec

Photo: CGES

Published

January 10, 2024

Country

Comments

comments icon

0

Share

Published:

January 10, 2024

Country:

Comments:

comments icon

0

Share

Montenegro’s transmission system operator CGES has signed another contract for the connection of a large solar power plant. The construction of the 240 MW facility is planned in Bijelo Polje, in the southern part of Montenegro.

CGES has so far signed three contracts for the grid connections for utility-scale photovoltaic facilities with a total capacity of 1,000 MW. The investors are M Energy, Sun Horizon and Obnovljivi Izvori Energije.

CGES said it signed an agreement with project firm EE Korita on the construction of infrastructure for connecting a EUR 200 million solar power plant to the transmission grid.

The investor is Danish firm European Energy

The contract, signed by Ivan Asanović, CEO of CGES, and Damir Banovec, the representative of EE Korita, represents a step toward strengthening the renewable energy production capacity and expanding the sustainable energy network, the TSO added.

The contract includes planning, construction and integration of the future solar power plant. According to CGES, the investor, Danish firm European Energy, has a significant background in the construction of PV facilities and wind farms.

Now CGES has contracts for the grid connection of four large solar power plants of an overall 1,240 MW. Of note, CEO Ivan Asanović said that without major investments the transmission grid could integrate renewable energy facilities with a total capacity of 1,500 MW.

The expected annual production is 331 GWh

Back in July, EE Korita submitted a request to the Environmental Protection Agency to decide whether an environmental impact assessment report was necessary for its PV facility.

The location for the power plant is owned by local firm Farma Moravac while the expected annual output is 331 GWh.

State institutions of Montenegro have issued a lot of permits for large solar power projects, but the country still doesn’t host a single one. However, three weeks ago the first ground-mounted solar power plant was put into operation.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

DNV acquire Automa Power Utilities digital operations energy

DNV to acquire Automa Power & Utilities, strengthening position as global end-to-end digital operations partner for energy industry

14 January 2026 - DNV agreed to acquire Brazil-based Automa, provider of integrated monitoring, control, and performance management solutions

montenegro epcg masdar agreement spajic djukanovic

EPCG, Masdar sign cooperation agreement

14 January 2026 - Montenegro’s power utility EPCG and UAE-based Masdar today signed a cooperation agreement as part of Abu Dhabi Sustainability Week

bih republic of srpska trebinje wind farm leotar Zhogbo Group

Zhongbo Group advances in preparation for construction of Leotar wind park

14 January 2026 - It would be the largest wind power plant in the Western Balkans by capacity and one of the largest in Southeast Europe

Montenegro renew first solar power auction call as soon as possible

Montenegro to renew first solar power auction call as soon as possible

14 January 2026 - Montenegro has disqualified all bidders in its first solar power auction and vowed to urgently remove procedural shortcomings and renew the call