Electricity

Italy’s TSO Terna advances project for another subsea power interconnection with Greece

Italy Terna subsea power interconnection Greece

Photo: Terna

Published

October 20, 2023

Country

Comments

comments icon

0

Share

Published:

October 20, 2023

Country:

Comments:

comments icon

0

Share

Italy and Greece are preparing to expand their electricity interconnection capacity to 1.5 GW by laying two cables of 1 GW in total on the seabed. Terna, the Italian transmission system operator, expects the investment to reach EUR 750 million.

Terna is conducting a public consultation procedure about its plan to install two submarine high-voltage direct current (HVDC) cables together with its Greek counterpart, the Independent Power Transmission Operator (IPTO or Admie). They aim to boost the interconnection between the two countries. The GR.ITA 2 line would go from Melendugno, on the Adriatic coast in Apulia, under the Strait of Otranto and Ionian Sea to Thesprotia (Tesprozia), located across the way from the southern tip of the island of Corfu.

The subsea section is planned to be 250 kilometers long. On the Italian side, the interconnector would also have an underground alternating current (AC) segment of 50 kilometers, to Galatina. It is the site of a future conversion station, according to Terna. Italy’s transmission also said system operator said it expects to invest EUR 750 million.

GR.ITA 2 would expand the total capacity on the border to 1.5 GW. The two companies commissioned the existing 400 kV interconnector in 2001. It runs through Otranto to Galatina. On the other side, the line lands in Aetos and continues to Arachthos.

Terna: Dialogue with institutions, associations and especially citizens will be essential for the project

Terna is holding a series of meetings with the representatives of institutions and local communities in seven affected municipalities in the province of Lecce. Dialogue with institutions, associations and especially citizens will be essential for the project, the company stressed.

The TSO already conducted a voluntary consultation last year. It said the process helped it prepare proposals for the locations of the transformer, the underground cables and the landing site.

The requirements that the company has decided to comply with voluntarily will allow for lower carbon dioxide emissions and energy consumption, the ability to choose locations that are structurally accessible and to promote products for recycling and reuse, according to the update.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment

Related Articles

Share coal power Finland nearly zero cogeneration plant shuts down

Share of coal power in Finland nearly zero as cogeneration plant shuts down

03 April 2025 - The now closed Salmisaari coal plant accounted for just 0.8% of the electricity mix in Finland together with three remaining ones

solar nuclear power prices europe eurelectric

Solar, nuclear lower Europe’s power prices by 30% in March

03 April 2025 - Solar broke a record in power generation in March for the third consecutive month, making up more than 10% of Europe’s electricity mix, Eurelectric said

PPC announces 5.8 billion plan for Western Macedonia, focused on photovoltaics, storage and data centers

PPC plans EUR 5.8 billion makeover of Western Macedonia coal region, including data centers

03 April 2025 - PPC presented a EUR 5.8 billion investment plan for the coal region of Western Macedonia in northern Greece

Eurowind Energy virtual PPA Romania automotive manufacturer

Eurowind Energy signs virtual PPA in Romania with automotive manufacturer

03 April 2025 - Autoliv contracted the supply of electricity from a wind park that Eurowind Energy built in Romania and Alight's solar project in Finland