Gross national electricity production participated with 68.1% in gross electricity consumption in Macedonia in June, according to data of the State Statistical Office.

Hydropower plants produced 55.2% of total electricity generation, thermal power plants covered 41.7%, wind parks produced 1.7%, while electricity output for solar and biogas power plants was 0.7% of the gross power generation.

Total consumption by types of energy commodities was 537.4 GWh of electricity, 3.75 million cubic meters of natural gas, 281,551 tonnes of coal and 114,698 tonnes of petroleum products, while 91.1% of the total national consumption of coal was used for electricity generation, statistical data show.

In the first half of the year, the average electricity retail price for households in Macedonia was MKD 5.02 (eight euro cents) per kilowatt-hour, a decrease of 1.65% compared to the last six months of 2015. The average price for the industry was between five and 13 euro cents without taxes.

Related Articles

Bistrica study pumped storage eps

Serbia moves closer to building Bistrica pumped storage hydropower plant

24 April 2026 - The construction of Bistrica will provide 55 GWh of energy storage capacity and enable the integration of 1.5 GW of renewables

serbia region eu energy community mou balkan green energy news lorkowski jovicic

Energy Community Secretariat, Balkan Green Energy News sign MoU to advance clean energy awareness across Balkans

24 April 2026 - The MoU outlines the framework for collaboration, ensuring accurate, timely, and balanced reporting while upholding the media's independence

bih republic of srpska dso elektrokrajina distribution grid loan ebrd

BiH’s DSO Elektrokrajina to invest EUR 30 million in distribution grid

24 April 2026 - The Council of Ministers of BiH has approved an initiative to begin negotiations for a loan aimed at upgrading the distribution grid

Serbia’s TSO EMS inks deal to invest EUR 36 million in substations

24 April 2026 - Works on substations in Bajina Bašta and Obrenovac are part of the third section of the Trans-Balkan Corridor for electricity transmission