Montenegrin state power utility Elektroprivreda Crne Gore (EPCG) has completed an overhaul of small hydropower plant Glava Zete, operated by its joint venture with Norwegian firm NTE. The state-owned utility has also replaced two transformers at its hydropower plant Perućica.

The modernization of Glava Zete was part of an EUR 8 million project that also included an overhaul of small hydropower plant Slap Zete, which has already been put in operation. Slap Zete is also owned by EPCG and NTE’s joint venture, according to a statement from EPCG.

The investment will boost electricity output by 30%

The project, which increased the hydropower plants’ efficiency, will result in a 30% increase in their electricity production, according to Dragan Vlahović, general manager of Zeta Energy, the joint venture which was founded in 2010 and is majority owned by EPCG. Annual electricity output is now expected to average 20.5 GWh, compared with 14.6 GWh prior to the overhaul.

The project also included the installation of state-of-the-art wastewater treatment technology, according to Vlahović. Both hydropower plants were built in the 1950s. Slap Zete has an installed capacity of 1.2 MW, while the capacity of Glava Zete is 4.5 MW.

The replacement of transformers at HPP Perućica will extend the lifespan by at least 30 years

The installation of two new transformers at HPP Perućica is part of a project to replace a total of five transformers, which has been agreed with a consortium led by Croatian company Končar.

The agreement, worth a total of EUR 2.25 million, envisages the delivery of two more transformers in 2021 and the last one in 2022, according to EPCG. However, Končar appears to be on track to deliver all three next year.

The replacement of these transformers will make Perućica a more reliable power plant, while the lifespan will be extended by at least 30 years, according to the plant’s general manager, Dragan Čizmović.

Early this year, Čizmović said a major overhaul of all seven generators at Perućica was underway and that generators 4, 5, and 7 were revitalized in 2018 and 2019. EPCG has recently launched an international tender for the preparation of project documentation for installing an eighth, 58.5 MW generator at Perućica.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Green for Growth Fund financial impact targets 2023

Green for Growth Fund tops its financial, impact targets in 2023

15 July 2024 - The Green for Growth Fund kept mitigating climate change and promoting sustainable economic growth last year in its 18 markets

IRENA La Camera renewables must grow higher speed scale

IRENA’s La Camera: Renewables must grow at higher speed, scale

12 July 2024 - IRENA's Director-General Francesco La Camera warned of ongoing patterns of concentration in geography in renewables deployment as well as against complacency

green steel electric vehicles study transport environment

Switching to green steel would add just EUR 8 per electric vehicle by 2040

11 July 2024 - Switching to 40% green steel would add just EUR 57 to the sticker price of an electric vehicle in 2030, according to an analysis by T&E

Albania declares eight winners at 300 MW solar power auction

Albania declares eight winners at 300 MW solar power auction

10 July 2024 - The lowest bid at Albania's solar power auction came in at EUR 39.7 per MWh, against a starting level of EUR 59.97 per MWh