ERS claims it would extend deadlines for the three hydropower plants on the Bistrica, citing force majeure due to the COVID-19 pandemic issues. Contractor AVIC-ENG from China is said to have the option to terminate the contract if funding isn’t found in less than two months and to keep the advance payment.

Elektroprivreda Republike Srpske, a state-owned energy company from Bosnia and Herzegovina, is late in the development of a project for a string of hydropower plants on Bistrica river. Namely, ERS has until September 4 to obtain financing or the contractor, AVIC-ENG – China National Aero-technology International Engineering, gets to keep the EUR 2 million advance payment, Capital.ba reported, citing the contract’s provisions.

ERS says there is “certain delay”

The deal signed in December for three hydropower plants on the Bistrica is worth EUR 120 million. The financial framework must be completed by September 4 and ERS acknowledged “a certain delay,” the article said.

The utility claimed the deadline would be extended due to force majeure, referring to the coronavirus pandemic. It also said HE Bistrica, the firm managing the project, has personnel limitations.

Hidroelektrane na Drini is responsible for finding loan

The complex in the country’s southeast was supposed to be installed within four years. In April, owners suggested Hidroelektrane na Drini, the subsidiary od ERS which controls the project, should secure the credit package.

According to the agreement, 85% of the expenses for the Bistrica hydropower plants will be covered from loans. The EUR 2 million advance payment was from a loan from Hidroelektrane na Drini to HE Bistrica, the concession holder.

ERS cited staffing issues at the HE Bistrica subsidiary

ERS initially sold HE Bistrica to Milenko Čičić’s Kaldera for EUR 3.5 million, after which Prointer acquired the firm. Then ERS bought it back for more than EUR 10 million, the report notes.

AVIC was earlier tapped for Drina hydropower cascade

The Bistrica hydropower plant cascade is planned to have 45 MW in combined capacity.

Separately, AVIC signed a memorandum of understanding in 2017 for the construction of hydropower plants Buk Bijela, Foča and Paunci on the nearby Drina river.

Elektroprivreda Srbije (EPS) runs the unrelated 60-year-old Bistrica hydropower plant across the border in Serbia.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Green for Growth Fund financial impact targets 2023

Green for Growth Fund tops its financial, impact targets in 2023

15 July 2024 - The Green for Growth Fund kept mitigating climate change and promoting sustainable economic growth last year in its 18 markets

IRENA La Camera renewables must grow higher speed scale

IRENA’s La Camera: Renewables must grow at higher speed, scale

12 July 2024 - IRENA's Director-General Francesco La Camera warned of ongoing patterns of concentration in geography in renewables deployment as well as against complacency

green steel electric vehicles study transport environment

Switching to green steel would add just EUR 8 per electric vehicle by 2040

11 July 2024 - Switching to 40% green steel would add just EUR 57 to the sticker price of an electric vehicle in 2030, according to an analysis by T&E

Albania declares eight winners at 300 MW solar power auction

Albania declares eight winners at 300 MW solar power auction

10 July 2024 - The lowest bid at Albania's solar power auction came in at EUR 39.7 per MWh, against a starting level of EUR 59.97 per MWh