ERS risks failure of Bistrica hydropower plants project on lack of funding

ERS failure Bistrica hydropower plants funding

Photo: Pixabay

Published

July 11, 2020

Comments

0

Share

Published:

July 11, 2020

Comments:

0

Share

ERS claims it would extend deadlines for the three hydropower plants on the Bistrica, citing force majeure due to the COVID-19 pandemic issues. Contractor AVIC-ENG from China is said to have the option to terminate the contract if funding isn’t found in less than two months and to keep the advance payment.

Elektroprivreda Republike Srpske, a state-owned energy company from Bosnia and Herzegovina, is late in the development of a project for a string of hydropower plants on Bistrica river. Namely, ERS has until September 4 to obtain financing or the contractor, AVIC-ENG – China National Aero-technology International Engineering, gets to keep the EUR 2 million advance payment, Capital.ba reported, citing the contract’s provisions.

ERS says there is “certain delay”

The deal signed in December for three hydropower plants on the Bistrica is worth EUR 120 million. The financial framework must be completed by September 4 and ERS acknowledged “a certain delay,” the article said.

The utility claimed the deadline would be extended due to force majeure, referring to the coronavirus pandemic. It also said HE Bistrica, the firm managing the project, has personnel limitations.

Hidroelektrane na Drini is responsible for finding loan

The complex in the country’s southeast was supposed to be installed within four years. In April, owners suggested Hidroelektrane na Drini, the subsidiary od ERS which controls the project, should secure the credit package.

According to the agreement, 85% of the expenses for the Bistrica hydropower plants will be covered from loans. The EUR 2 million advance payment was from a loan from Hidroelektrane na Drini to HE Bistrica, the concession holder.

ERS cited staffing issues at the HE Bistrica subsidiary

ERS initially sold HE Bistrica to Milenko Čičić’s Kaldera for EUR 3.5 million, after which Prointer acquired the firm. Then ERS bought it back for more than EUR 10 million, the report notes.

AVIC was earlier tapped for Drina hydropower cascade

The Bistrica hydropower plant cascade is planned to have 45 MW in combined capacity.

Separately, AVIC signed a memorandum of understanding in 2017 for the construction of hydropower plants Buk Bijela, Foča and Paunci on the nearby Drina river.

Elektroprivreda Srbije (EPS) runs the unrelated 60-year-old Bistrica hydropower plant across the border in Serbia.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

europe flexibility seasonal balancing iea report

Flexibility needs to be met by demand response, batteries, hydrogen, but also thermal, hydropower plants – IEA

03 May 2024 - The report Managing the Seasonal Variability of Electricity Demand and Supply analyzes the situation in Europe, India, and Indonesia

IPTO suspends all electricity imports until May 7 to protect the Greek system

Greece suspends electricity imports until May 7 to protect system

03 May 2024 - The Greek Independent Power Transmission Operator (IPTO) has announced the suspension of all electricity imports during the hours around noon

Two agrosolar power plants are planned to be constructed in Serbia

Two agrisolar projects launched in northern Serbia

02 May 2024 - In the vicinity of Kikinda in Serbia, two new agrisolar projects are underway: Solar Power Plant Delta and Brankov solar

el-dorado-electricity-imports-north-macedonia-rke

North Macedonia: ‘Solar El Dorado’ cuts electricity imports to 2.75%

02 May 2024 - In 2023, North Macedonia's new solar capacity increased by as much as 251% compared to 2022