Nexans strengthens wind power transmission capacity

Published

December 9, 2015

Comments

comments icon

0

Share

Published:

December 9, 2015

Comments:

comments icon

0

Share

EnergoBit SA’s 30 MW Babadag III wind farm in Romania will transmit energy to the grid using 140 kilometres of Nexans SA’s high temperature conductor cables and accessories.

The existing Babadag – Tulcea Vest 110 kV power line does not have enough capacity to carry power from the solar plant, Nexans said. The high temperature ACSS/TW Brant conductors will double the line rating without adding mechanical loads, the company’s statement said. Upgrading the conductor along the 44 kilometre route allows the wind farm to operate with existing infrastructure, according to the press release.

With a capacity of 194 megavolt-amperes, the new power line is able to carry 63% more current than the existing system when operating at the same temperature. The ACSS conductors also allow for a 16% reduction in joule losses when operating at the same current as the existing ACSR system, the specifications say.

Babadag 3 is in Dobruja (Dobrogea), southeast Romania. The conductors will be manufactured at Nexans’ Benelux plant in Elouge, Belgium.

Related Articles

Romania launches renewables auction for 3 5 GW

Romania launches renewables auction for 3.5 GW

13 May 2025 - The Romanian Ministry of Energy issued a call for 3.47 GW of wind and solar power capacity. The deadline for submissions is July 11.

Citizens and activists in bulgaria oppose wind farm project that would destroy forest

Citizens, activists in Bulgaria oppose wind farm project that would destroy forest

13 May 2025 - In the Avren municipality of Bulgaria, citizens and activists are preparing a protest against a planned wind farm that would result in the felling of 30 hectares of forest.

blackout spain portugal entso report

Blackout in Spain, Portugal started with 2,200 MW power production loss

12 May 2025 - ENTSO-E has published the sequence of relevant events from an incident on April 28 that caused a total blackout in Spain and Portugal

bih citizen energy renewable energy communities republic of srpska miljevic

Significant step for citizen energy in BiH – Republic of Srpska enables establishment of first renewable energy communities in region

12 May 2025 - The Republic of Srpska, one of the two entities making up BiH, adopted a rulebook on renewable energy communities