EnergoBit SA’s 30 MW Babadag III wind farm in Romania will transmit energy to the grid using 140 kilometres of Nexans SA’s high temperature conductor cables and accessories.

The existing Babadag – Tulcea Vest 110 kV power line does not have enough capacity to carry power from the solar plant, Nexans said. The high temperature ACSS/TW Brant conductors will double the line rating without adding mechanical loads, the company’s statement said. Upgrading the conductor along the 44 kilometre route allows the wind farm to operate with existing infrastructure, according to the press release.

With a capacity of 194 megavolt-amperes, the new power line is able to carry 63% more current than the existing system when operating at the same temperature. The ACSS conductors also allow for a 16% reduction in joule losses when operating at the same current as the existing ACSR system, the specifications say.

Babadag 3 is in Dobruja (Dobrogea), southeast Romania. The conductors will be manufactured at Nexans’ Benelux plant in Elouge, Belgium.

Related Articles

croatia ante susnjar minister renewables subsidies jutarnji list energy conference

Šušnjar: Croatia allocated EUR 4 billion so far to boost renewables; subsidies for wind, solar to end

28 January 2026 - Minister of Economy Ante Šušnjar said at an energy conference that the money could have been put to better use

končar power transformer tanks Siemens factory

Croatia’s Končar to invest EUR 500 million in manufacturing over three years

27 January 2026 - Končar has opened a power transformer tank factory with Siemens Energy and it plans to develop anti-drone protection for energy facilities

Research project in Romania explores the use of agrisolar systems with batteries in agriculture

Researchers in Romania developing agrisolar system with batteries

27 January 2026 - An agrisolar power plant with batteries is being set up in a research and demonstration project in Romania

Fortis Energy break ground on hybrid power plant in Serbia by mid 2026

Fortis Energy to break ground on hybrid power plant in Serbia by mid-2026

27 January 2026 - Fortis Energy is set to install a 36 MWh battery energy storage system for its Noćaj 1 photovoltaic project in Serbia, of 135 MW