Lešće hydro plant got EUR 131,000 for rehabilitation

Published

September 4, 2015

Comments

comments icon

0

Share

Published:

September 4, 2015

Comments:

comments icon

0

Share

Estimates that the state-owned power company HEP had given before the construction of hydro power plant Lešće weren’t accurate, said Jagoda Munić from Green Action, portal H-alter reported. After the company acknowledged it spent HRK 1 million (EUR 131,000) to mitigate the environmental damage the facility caused, she stressed this is an example of what the projects of Ombla and Kosinj may have caused.

During the construction of the plant in central Croatia, launched in 2010, the expenses turned out to be EUR 40 million bigger than predicted. The organization had HEP report on the rehabilitation costs by insisting on the Law on the Right to Access Information. The company conceded long-term repair programme still needs to be devised.

Green Action said the 42 MW power plant caused intensive erosion downstream from the dam, hurt fish stock and destroyed local roads. Also, the microclimate has changed and the damage to biodiversity can’t even be estimated, activists said.

Related Articles

masdar socar green solar power projects azerbaijan

Masdar, SOCAR join forces on 760 MW of solar in Azerbaijan

23 November 2024 - Masdar and SOCAR Green have reached financial close for the 445 MW Bilasuvar and 315 MW Neftchala solar projects in Azerbaijan

wind farm ljubusa tomislavgrad

Concession signed for 80 MW wind farm in Tomislavgrad

22 November 2024 - Alpha Wind has been granted a concession to build the 80 MW Ljubuša wind farm in the municipality of Tomislavgrad.

zagreb waste management center tomasevic

Zagreb picks technological solution for city’s waste management system

22 November 2024 - The city has selected technological solution C, one of three proposed, based on an analysis of municipal waste processing technologies

Dentons advises EnergoNuclear EPCM deal Cernavoda

Dentons advises EnergoNuclear on EPCM deal for Cernavodă project

22 November 2024 - Dentons advised EnergoNuclear on an engineering, procurement, and construction management (EPCM) contract for Cernavodă 3 and 4