EPS to transform to JSC in 2020, tariff review for 2018 to be completed by end-August, Serbia tells IMF

EPS to transform to JSC in 2020, tariff review for 2018 to be completed by end-August, Serbia tells IMF

Photo: EPS

Published

July 26, 2018

Country

Comments

comments icon

0

Share

Published:

July 26, 2018

Country:

Comments:

comments icon

0

Share

The legal status of public power utility Elektroprivreda Srbije (EPS) will be changed to a joint-stock company in 2020, while a tariff review for 2018 will be completed by the end of August with the assistance of the World Bank, the Serbian authorities wrote in the program statement concerning the new Policy Coordination Instrument (PCI) recently approved by the International Monetary Fund (IMF).

EPS’ legal status will be changed to a joint-stock company in line with the ongoing corporate restructuring process and financial consolidation, aiming to improve the viability of the company and ensure its professional management, according to the text of the program statement concerning the PCI, which the IMF Executive Board approved on July 18.

“We have continued implementing the 2016–19 labor optimization plan. We have engaged the World Bank and the EBRD [European Bank for Reconstruction and Development] to support our plan to enhance corporate governance, management, and procurement and planning frameworks,” the Serbian authorities wrote.

In March, the World Bank approved the Second Public Expenditure and Public Utilities Development Policy Loan (PEPU DPL 2), in the amount of EUR 160.6 million, to support the Serbian government’s multi-year effort to raise the efficiency and effectiveness of public spending as well as the transformation of the energy and transport sectors, including EPS.

PEPU DPL 2 will support EPS in achieving increased convergence of the guaranteed electricity supply tariff to reach market parity levels from 64% at end-2014 to 80% at end-2018, conditional on the analysis of the financial position of the company and the adequacy of resources for needed investments, the World Bank said in a press release at the time.

In line with the tariff methodology for the public supplier, the convergence will be measured by the difference between the guaranteed supply price charged by EPS and the prevailing regional wholesale price set on the basis of neighboring power exchanges (Hungarian exchange HUPX), according to the documentation posted on the World Bank’s website.

Among the goals of the operation is to increase the number of total beneficiaries of the Energy Vulnerable Program, from 60,600 households in 2014 (of which 27% were female headed households) to 70,000 households in 2018 (of which 30% are female headed households).

The loan will also back EPS’s efforts to optimize its labor force targeting an increase in the education level of EPS workforce, according to the March press release.

EPS made a net profit of around RSD 3.4 billion (about EUR 28.8 million) in 2017, as its distribution subsidiary EPS Distribucija ended the year RSD 2.4 billion (about EUR 20.3 million) in the black, according to unconsolidated audited financial reports posted on EPS’ website.

Tags: , ,
Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Fortis Energy Albania 62 MW solar power

Fortis Energy gets green light in Albania for 62 MW solar power project

27 June 2025 - Fortis Energy received approval from the Albanian government for the construction of a 62 MW solar power plant in the country's southeast

Hidroelectrica construction pilot floating photovoltaic plant

Hidroelectrica to begin construction of its pilot floating photovoltaic plant

27 June 2025 - Romanian state-owned hydropower plant operator Hidroelectrica picked the contractor for a 10 MW floating solar power plant, its first

Satellite dishes get new life hosting solar panels for data center

Satellite dishes get new life, hosting solar panels for data center

26 June 2025 - A Swiss firm converted its unused satellite dishes into solar dishes to power its data center, using SolarEdge-s inverters and optimizers.

Solar power exceeds Bulgaria entire electricity demand first time

Solar power exceeds Bulgaria’s entire electricity demand for first time

25 June 2025 - For the first time, photovoltaic production alone surpassed power consumption in Bulgaria – for two hours