Suzlon to use fewer, stronger turbines for 25 MW Ivan Sedlo wind park

Suzlon turbines 25 MW Ivan Sedlo wind park

Photo: Unsplash

Published

August 19, 2020

Comments

comments icon

0

Share

Published:

August 19, 2020

Comments:

comments icon

0

Share

The subsidiary of a Danish-based company requested another environmental permit after revising the project for a wind power plant near Sarajevo. Suzlon said the Ivan Sedlo facility would consist of five instead of 12 units.

The Ministry of Environment and Tourism of the Federation of Bosnia and Herzegovina said Suzlon Wind Energy BH filed a request for an environmental permit for the planned Ivan Sedlo wind power plant. Interested parties can send suggestions by August 25.

Power plant to take up less space 

The plan was for 12 turbines and the firm obtained an environmental permit two years ago, but now it revised it to five units, which would be purchased from Siemens Gamesa. It means the affected area in the municipality of Hadžići will be smaller, according to the subsidiary of Denmark-based Suzlon Wind Energy.

Suzlon revealed annual output is projected at 78.3 GWh

It revealed the planned capacity for the facility southwest of Sarajevo remains at 25 MW. The firm expressed interest in the project all the way back in 2008. In the meantime, it scrapped the version with 22 turbines, and subsequently also the possibility to build 19 turbines with an overall 39.9 MW.

The Sarajevo Canton signed a 30-year concession agreement with Suzlon in May 2018. At the time, local authorities estimated the investment at EUR 30 million. Test results have shown an average wind speed of 7.7 meters per second at the Ivan sedlo mountain pass.

Turbines at elevations of as much as 1,526 meters

The aggregates will be at least 300 meters apart, the company said in its statement on the measures to lower the impact on the local flora and fauna. The units would be installed at between 1,172 and 1,526 meters above sea level, according to the documentation.

Siemens Gamesa’s SG 5.0-145 turbines will be on 102.5-meter high towers and the diameter will be 145 meters, Suzlon said and added annual production would be 78.3 GWh. The nearest villages are Mrkajići, Vukovići and Bradina.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

PPC to invest 24 billion with a focus on Balkan expansion

PPC to invest EUR 24 billion with focus on Balkan expansion

27 April 2026 - PPC boosted its investment plan to EUR 24 billion by the end of the decade, with a focus on renewable energy, gas power plants and data centers

Bistrica study pumped storage eps

Serbia moves closer to building Bistrica pumped storage hydropower plant

24 April 2026 - The construction of Bistrica will provide 55 GWh of energy storage capacity and enable the integration of 1.5 GW of renewables

serbia region eu energy community mou balkan green energy news lorkowski jovicic

Energy Community Secretariat, Balkan Green Energy News sign MoU to advance clean energy awareness across Balkans

24 April 2026 - The MoU outlines the framework for collaboration, ensuring accurate, timely, and balanced reporting while upholding the media's independence

EPCG Masdar establishing renewables joint venture in Montenegro

EPCG, Masdar establishing renewables joint venture in Montenegro

24 April 2026 - EPCG and Masdar are starting a JV in Montenegro with 50% ownership each, for clean energy projects across multiple technologies