11 June 2021 - Power utility Elektroprivreda Republike Srpske plans to build hydropower plants and PV facilities, while wind farms will not be in its focus.
10 June 2021 - The workshop “Gender dimensions in the sustainable management of natural resources through a Nexus approach in the Drina River Basin” is to take place on June 23. Read more and register.
07 June 2021 - Unnamed sources said the construction of unit 7 in thermal power plant Tuzla most probably won't proceed as GE decided not to supply the equipment
01 June 2021 - The EBRD is interested in providing financial support to the construction of Trebinje 1, ERS's first solar power plant.
28 May 2021 - Integrated management of water, energy, and land resources, while protecting ecosystems, remains a substantial challenge in the Western Balkans.
27 May 2021 - HE na Vrbasu is developing a solar power plant project, the second in the portfolio of state-owned power utility Elektroprivreda Republike Srpske
24 May 2021 - Elektroprivreda Hrvatske Zajednice Herceg Bosne has issued a public call for the purchase of renewable energy projects.
21 May 2021 - EPBiH intends to include CO2 expenses in its financial reports from next year at the initiative of the Energy Community Secretariat
20 May 2021 - Government-owned utility EPBiH said it would reduce the number of employees in its seven coal mines to get the subsidiaries on a firm footing
18 May 2021 - The improvements are expected to bring annual savings of about EUR 700,000 annually, reduce air pollution and CO2 emissions.
17 May 2021 - The planned capacity of the hydropower plant in the municipality of Foča is 93 MW while the expected annual production is 332 GWh.
13 May 2021 - The amount exceeds the total cost of coal power production and it would make the activity unprofitable.
04 May 2021 - A groundbreaking ceremony for hydropower plant (HPP) Buk Bijela on the Drina river, a joint project of Serbia and the Serb-dominated entity Republic of Srpska, will take place on May 17.
20 April 2021 - The Sarajevo Canton picked 77 beneficiaries that will install wood pellet furnaces and 27 are setting up heat pumps instead of coal for heating
06 April 2021 - Elektroprivreda Republike Srpske needs funding for three hydropower plants on the Bistrica river and HPP Dabar.
01 April 2021 - The Government of FBiH wanted to allow an extension after a period of 12 years during which SHPPs receive subsidies.