Batteries for photovoltaics to get priority status in Greece

Batteries for photovoltaics get priority status in Greece

Photo: freepik.com

Published

October 17, 2024

Country

Comments

comments icon

0

Share

Published:

October 17, 2024

Country:

Comments:

comments icon

0

Share

The Greek Ministry of Environment and Energy submitted its new bill of law to parliament with measures for renewable energy and battery energy storage.

One of the most important changes is that the installation of a behind-the-meter battery in photovoltaic plants would benefit from a fast-track licensing procedure. It concerns projects that have become operational after July 4, 2019, as well as the ones that acquired connection terms. The batteries need to have at least one hour of operation at the plant’s maximum capacity to be included.

Remuneration would be calculated according to the hourly price in the day-ahead market (DAM), for quantities delivered to the grid. On the other hand, the framework wouldn’t include any subsidies.

This way, the ministry aims to add 1.5 GW to 2 GW of storage on top of 1 GW of standalone battery installations awarded through auctions. Battery systems can also be installed in decommissioned lignite power plants, to support the system with up to 450 MW in total.

Greece’s goal is to reach about 3.5 GW in battery storage by 2030 to support its ever-increasing renewables fleet.

So far, the first two auctions for standalone batteries have been completed and the third one is expected by the end of this year. According to Independent Power Transmission Operator (IPTO), connection terms have been issued for 18 units, with an overall capability of 651.3 MW. In total, 321 energy storage projects around the country have applied to IPTO for connection terms.

Boost for floating photovoltaics, small renewables units

Other changes brought by the proposed law include pilot projects for floating photovoltaics in artificial lakes. Units can be up to 8 MW each, for a total of 80 MW.

Last but not least, grid space would be allocated for small hydropower and biomass plants and small wind turbines, to diversify the renewables mix within the distribution network.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

Enery commissions PPA backed PV plant Tsenovo 113 MW Bulgaria

Enery commissions PPA-backed PV plant of 113 MW in Bulgaria

17 October 2024 - Enery inaugurated its largest solar power facility. The 113 MW unit is in Tsenovo in northeastern Bulgaria.

Batteries for photovoltaics get priority status in Greece

Batteries for photovoltaics to get priority status in Greece

17 October 2024 - The Greek Ministry of Environment and Energy submitted its new bill of law with measures for renewable energy and battery energy storage

serbia solar 1 GW ugt hyundai signing agreement

Serbia signs agreement with Hyundai Engineering-UGT Renewables for 1 GW of solar

16 October 2024 - The strategic partnership agreement between Serbia and the Hyundai Engineering-UGT Renewables consortium was signed in Belgrade

Solar wind projects of over 10 GW in Albania await grid access transmission

Solar, wind projects of over 10 GW in Albania await grid access

16 October 2024 - Albania's Transmission System Operator (OST) said in the 2023 report that 133 wind and solar power projects applied for grid connections