ERS opens 8.76 MW hydropower plant Bočac 2 under EUR 21.5 million investment

Photo: Integral Inženjering

Published

October 4, 2018

Comments

comments icon

0

Share

Published:

October 4, 2018

Comments:

comments icon

0

Share

Power utility Elektroprivreda Republike Srpske (ERS) yesterday unveiled the Bočac 2 hydropower plant (HPP) with an installed capacity of 8.76 MW and the expected annual output of 41.6 GWh of electricity. The project worth BAM 42 million (about EUR 21.5 million) is expected to break even within seven years.

Alongside HPP Bočac 2, which will create 32 jobs, a newly built small hydropower plant (SHPP) with an installed capacity of 586 kW close to HPP Bočac 1 was also unveiled. The SHPP will serve for the self-consumption of Hidroelektrane na Vrbasu, a subsidiary of ERS.

Hidroelektrane na Vrbasu, the direct investor in the project, states on its website that HPP Bočac 2 has no adverse impact on the environment, while it uses a clean and renewable energy source.

Foto: Integral Inženjering

Laktaši-based Integral Inženjering carried out the construction works, while Banja Luka-based Elnos BL delivered equipment. The design, consultancy services, and supervision were provided by Belgrade, Serbia-based Jaroslav Černi institute for the development of water resources.

Hidroelektrane na Vrbasu General Manager Nedeljko Kesić said at the unveiling ceremony that the feasibility study projects annual revenues from the new HPP’s electricity sales at BAM 5.5 million (around EUR 2.81 million), local media reported.

HPP Bočac 2 is located 7 km downstream from HPP Bočac 1, which was built 37 years earlier.

The unveiling ceremony, held at the peak of election campaigning, was attended by Republika Srpska President Milorad Dodik, as well as Minister of Industry, Energy, and Mining Petar Đokić, who recalled that Republika Srpska has opened three energy facilities over the past few years – HPP Mesići-Nova, HPP Bogatići Nova, and HPP Bočac 2.

HPP Bogatići Nova on the Željeznica river near Sarajevo was put into operation exactly a month ago. The 9.96 MW HPP soaked an investment of BAM 18.5 million (around EUR 9.45 million). HPP Bogatići Nova should produce an average 46.26 million kWh of electricity annually.

HPP Bogatići Nova is expected to have annual revenues of BAM 5 million (about EUR 2.55 million).

The Mesići-Nova small hydropower plant (SHPP) near Rogatica, with an installed capacity of 5 MW, broke even on the BAM 10 million (EUR 5 million) investment after three and a half years of operation, Ljubomir Mrda, director of ERS subsidiary Elektrodistribucija Pale, said recently.

Comments (0)

Be the first one to comment on this article.

Enter Your Comment
Please wait... Please fill in the required fields. There seems to be an error, please refresh the page and try again. Your comment has been sent.

Related Articles

croatia wind farm cemernica vsb totalenergies

TotalEnergies developing 80 MW Čemernica wind farm in Croatia

10 April 2026 - The Čemernica wind farm is planned to be built in the municipality of Dicmo and the city of Trilj, near the coastal city of Split

eu first cbam certificate price european commission

European Commission sets first CBAM certificate price

10 April 2026 - The European Commission has published the first price of CBAM certificates for 2026 Q1 on its new dedicated page on the CBAM website

Serbia’s Đedović Handanović in Azerbaijan for discussions on gas projects

08 April 2026 - Serbian Minister Dubravka Đedović Handanović met in Baku with Azerbaijani ministers and the head of SOCAR

croatia rimac technology new bmw i7 sedan battery

BMW, Rimac to unveil fully electric i7 on April 22

08 April 2026 - The new BMW i7 will be the first BMW Group BEV to feature a jointly developed battery system, manufactured at the Rimac Campus near Zagreb